JNC LOGISTICS, THLG member for China, is currently handling an ongoing project for the contstruction of Xi'an Proton Therapy Center.
Xi'an Proton Therapy Center is the sixth medical institution in China to obtain the license for proton radiation therapy system, which is of milestone significance for cancer treatment in Northwest China.
In terms of equipment, the project has selected a Medical Proton Therapy System, and we are fortunate enough to become the transportation and positioning supplier for this system.
The project has been continuing from the beginning of 2024, until the end of 2024.
Cargo details
- 1 x Cyclotron 6,37 x 4,26 x 3,45 m = 95000 kgs
- 1 x Polecap 6,37 x 3,47 x 3,45 m = 38000 kgs
- 2 x Gantry Body each 9,69x3,50x3,85 m = 55000 kgs
- By Ro-Ro service from Antwerp to Shanghai
- More than 30 OOG containers from Rotterdam to Shanghai
- Final destination: Xi’an, Shanxi, about 1500km
Safety and Risk Management
- Ultra long distance transportation:it’s about 1500km from Shanghai to Xi’an Jobsite.
- Load –bearing of the ground of RORO terminal which cant not afford the weight of cargo, we need to increase road weighting capacity and use axis trucks.
- The ground for operation at site has a slope with high difference, we use two excavators and assistive tools to help the truck into position.
- Based on the site situation, we are fully involved in the road renovation planning throughout the entire process.
- Engineering and position of the cargo.
- We use an 800 ton crawler crane to complete the operation in a very narrow working area (width 16.5 meters).
- The ground hardness cannot meet the weighing requirements, so we have made modifications to the on-site road surface hardness in the later stage.
- Reduced the slope of the positioning platform.